高级检索

    多次采动下邻空巷道围岩变形破坏机理及稳定性控制技术

    Surrounding rock deformation and failure mechanism and stability control technology of gob-side roadway under multiple mining

    • 摘要: 以小保当煤矿11盘区内工作面采取双巷掘进而导致邻空巷道围岩先后遭受两次采动扰动为出发点,综合运用现场调研、弹性力学、数值模拟和工业性试验的方法,对邻空巷道围岩变形破坏机理进行了充分研究。结果表明,上区段工作面一次采动影响下,邻空巷道位于厚硬顶板岩层破断所形成的外应力场影响范围区,其围岩先后经历初期慢速增加、中期快速增加、后期高速增加和末期缓慢稳定4个变形阶段,且以工作面滞后测点100 m至超前测点460 m的变形阶段为主要变形破坏阶段;邻空巷道围岩变形阶段的本质诱因为厚硬顶板运移变化,其对应可划分为初始挠变运移区、中期快速下沉运移区、后期加剧下沉运移区和末期缓慢下沉运移区 4个区间;本区段工作面二次采动影响下,煤壁前方形成的L型应力集中区将加剧邻空巷道超前段围岩的变形破坏程度,叠加应力超前影响范围约120 m,对应峰值位置超前煤壁20.5 m。通过地表施工L型钻井,其XBD-03L水平井段预致裂范围充分覆盖了邻空巷道正上方厚硬顶板岩层,同期对巷道围岩采取非对称优化支护方案,压裂影响区内工作面中上部支架工作阻力控制在30 MPa以内,来压步距、来压持续距离和动载系数平均值分别下降至12.4 m、10.8 m和1.42,邻空巷道超前段围岩平均变形量维持在0.1 m以下,巷道围岩控制效果良好。

       

      Abstract: Based on the twice mining disturbances of the surrounding rock of the gob-side roadway caused by the double roadway excavation in the 11 panel area of Xiaobaodang Coal Mine, the surrounding rock deformation and failure mechanism of the gob-side roadway are fully studied by using the methods of field investigation, elastic mechanics, numerical simulation and industrial test. The results show that under the influence of the first mining of the upper section working face, the gob-side roadway is located in the influence range of the external stress field formed by the fracture of the thick and hard roof strata. The surrounding rock will experience four deformation stages: slow increase in the initial stage, rapid increase in the middle stage, rapid increase in the later stage and slow stability in the final stage. The deformation stages from the lagging measuring point 100 m to the leading measuring point 460 m are the main deformation and failure stages. The essential cause of stages of surrounding rock deformation in the gob-side roadway is the migration of the thick and hard roof, which can be divided into four intervals: the initial deflection migration area, the medium-term rapid subsidence migration area, the later intensified subsidence migration area and the final slow subsidence migration area; under the influence of the secondary mining of the working face in this section, the L-shaped stress concentration area formed in front of the coal wall will aggravate the deformation and failure degree of the surrounding rock in the advance section of the gob-side roadway. The superimposed stress advance influence range is about 120 m, and the corresponding peak position is 20.5 m ahead of the coal wall. Through the surface construction of L-shaped drilling, the pre-cracking range of XBD-03 L horizontal well section fully covers the thick and hard roof strata directly above the gob-side roadway. At the same time, the asymmetric optimization support scheme is adopted for the surrounding rock of the roadway. The working resistance of the middle and upper supports in the working face in the fracturing affected area is controlled within 30 MPa, and the average values of the pressure step distance, the pressure duration distance and the dynamic load coefficient are reduced to 12.4 m, 10.8 m and 1.42, respectively. The average deformation of the surrounding rock in the leading section of the gob-side roadway is maintained below 0.1 m, and the surrounding rock control effect of the roadway is good.

       

    /

    返回文章
    返回